Is there a way to easily pause/turn off all broadcast reports?
As part of an upgrade procedure (7.2->7.3+) we want to make sure the client's broadcasts aren't being sent and also aren't queuing prior to the system coming back online.
Cheers,
Peter
Hi Peter,
I hope all is well,
I would highly recommend following our Wiki instructions on our Schedule Management: http://wiki.yellowfin.com.au/display/USER73Plus/Schedule+Management
Within this link we have a section covering Pause Scheduled Task. Unfortunately this would work by pausing each individual Broadcast.
Regards,
Mark
Hi Peter,
I hope all is well,
I would highly recommend following our Wiki instructions on our Schedule Management: http://wiki.yellowfin.com.au/display/USER73Plus/Schedule+Management
Within this link we have a section covering Pause Scheduled Task. Unfortunately this would work by pausing each individual Broadcast.
Regards,
Mark
Hi Mark,
All good thanks.
I was hoping for an easier way to pause 60-70 broadcasts in "one click". Maybe there's something in the database we can try?
Regards,
Peter
Hi Mark,
All good thanks.
I was hoping for an easier way to pause 60-70 broadcasts in "one click". Maybe there's something in the database we can try?
Regards,
Peter
Hi Peter,
I hope all is well,
Looking into this further I can recommend the following options:
With the above I would highly recommend Option 1, reason being it won't impact other schedules like filters, ldap, event archiving, although as we are aware this would be a slightly longer process for opening each individual (60+) broadcast.
Let me know what you think Peter, I look forward to your reply.
Regards,
Mark
Hi Peter,
I hope all is well,
Looking into this further I can recommend the following options:
With the above I would highly recommend Option 1, reason being it won't impact other schedules like filters, ldap, event archiving, although as we are aware this would be a slightly longer process for opening each individual (60+) broadcast.
Let me know what you think Peter, I look forward to your reply.
Regards,
Mark
Hi Peter,
I hope all is well,
I just want to touch base and question whether my last email/post was enough to assist with your question. If you can please get back to me asap I would appreciate this greatly. I look forward to your reply.
Regards,
Mark
Hi Peter,
I hope all is well,
I just want to touch base and question whether my last email/post was enough to assist with your question. If you can please get back to me asap I would appreciate this greatly. I look forward to your reply.
Regards,
Mark
Hi Mark,
We haven't progressed with the upgrade just yet so I can't give you a solid answer on that sorry.
I think also we found an option from the db update bim_prod_repo.taskschedule set ScheduleIsOn = 0 or 1. Again, we haven't been able to test this yet either.
I suspect updating the web.xml is a better/easier option than the db though.
Cheers,Peter
Hi Mark,
We haven't progressed with the upgrade just yet so I can't give you a solid answer on that sorry.
I think also we found an option from the db update bim_prod_repo.taskschedule set ScheduleIsOn = 0 or 1. Again, we haven't been able to test this yet either.
I suspect updating the web.xml is a better/easier option than the db though.
Cheers,Peter
Hi Peter,
Thank you for getting back to me. I will go ahead and mark this Question as Answered although an update with how you get on would be great.
Regards,
Mark
Hi Peter,
Thank you for getting back to me. I will go ahead and mark this Question as Answered although an update with how you get on would be great.
Regards,
Mark